Wednesday, October 27, 2010

Roof decking continues



2nd Floor Kids Playroom

Monday, October 25, 2010

Roof and second floor are well on their way

It's really starting to look like the final product now. First floor framing is basically complete. Second floor rooms are roughed in and the roof is starting to go on. The roof trusses should be delivered later this week. We ordered the garage doors today, too!





Thursday, October 21, 2010

First floor framing mostly complete, they started on the second floor today


Outdoor kitchen patio.

Shelly and Pearson standing in the front door opening.

Shelly showing off her huge walk in closet.

P likes the way the new house is coming along.

Stairwell upstairs from the Great Room.

View of the kitchen and nook from the top of the stairs.

Fireplace

Entryway and Dining Room from the Great Room

Wednesday, October 13, 2010

Tuesday, October 12, 2010

Basement floor poured




Garage floor ready to be poured tomorrow.

Friday, October 1, 2010

Footers are poured, subsoil drainage in



A new friend came to welcome us and check out our progress (no tree stands allowed, Scott)

And she brought her baby