Thursday, September 30, 2010

Framed footers, should be ready for concrete tomorrow

View of basement from NE corner

Shelly and Pearson in front of garage

Footers under kitchen

View of garage from the SE corner.

Tuesday, September 28, 2010

Layout and Excavation

New basement grade is about three feet below the old one.

White paint marks the new front corner of my Garagmahal.

And there's the breakfast nook laid out.

Monday, September 27, 2010

Tuesday, September 14, 2010

Sewer Install Underway

Directional boring machine.
1,200 feet of 2" EPDM sewer pipe.  Last time it will be clean. . . ever.



Tuesday, July 27, 2010

Sewer Permit is approved in concept, but still a few more details to iron out.

Almost a year later and we've finally gotten agreement on how to proceed.  Just need to finalize a few more drawings and we should be close. 

Sunday, November 1, 2009

Applied for the sewer permit

After several months of going back and forth with the city, we've finally submitted our plans.  Time to wait and see.